£800,000 of refurbishment savings agreed ‘offline’ with contractor Rydon, including cheaper cladding

The Grenfell Tower landlord held a secret meeting to cut refurbishment costs – including discussing the switch to cheaper cladding – despite being warned by lawyers it would break procurement law and could void the main contract, the public inquiry into the disaster was told.

David Gibson, head of capital investment at the Kensington and Chelsea Tenant Management Organisation (KCTMO), which operated the council tower block for its owner, the Royal Borough of Kensington and Chelsea, organised a “secret” and “offline” meeting with the contractor Rydon in which they agreed more than £800,000 in savings, he told the inquiry on Thursday.

Continue reading…

You May Also Like

UK defence secretary rejects calls from Ukraine for no-fly zone

Ben Wallace says air exclusion zone would ‘lead to war against Russia…

Covid scheme: UK government to cover 22% of worker pay for six months

Rishi Sunak outlines plans that will take over from furlough programme Key…

‘Not sustainable’: England’s teachers on coping with Covid

Pressure on schools is leading to low morale and burnout among even…